The 1,862 central government infrastructure projects still under construction were approved at ₹34.83 lakh crore. Their revised cost now stands at ₹38.11 lakh crore. That gap of ₹3.28 lakh crore, or 9.4%, is the infrastructure cost overrun in the October 2026 Flash Report from the Ministry of Statistics and Programme Implementation (MoSPI), which went out with a PIB release at 4:00 PM IST on 25 November.
The release led with ₹17.87 lakh crore already spent. We took the ministry-wise table at the back of the report and asked a different question: where did the budgets grow?

Where the infrastructure cost overrun sits
Railways has the largest overrun in rupees. Its 288 projects were approved at ₹6.02 lakh crore and now cost ₹7.38 lakh crore, a rise of ₹1.35 lakh crore or 22.5%. That is 41% of the whole overrun.
Water Resources is the sharper case in percentage terms. Its 33 projects were approved at ₹97,485 crore and are now costed at ₹1.93 lakh crore, up 97.8%. They have already spent ₹1.35 lakh crore, more than their entire original budget. One project explains about half of that jump: the Polavaram irrigation project, listed at an original ₹10,151 crore and a revised ₹55,549 crore, adds ₹45,398 crore on its own.
Together, the two ministries hold 17% of the projects and 20% of the original cost, but 70% of the overrun.
Roads tell the opposite story. The road ministry runs 972 projects, more than half the list and 27% of the original cost, yet its revised cost is only 1.5% above approval. Power (9.1%) and petroleum and natural gas (9.5%) sit close to the overall average. Telecom is the outlier on the other side: its 31 projects are now costed ₹25,087 crore below their original approval, a 15.8% cut that pulls the net total down. Without the ministries whose costs fell, the gross overrun would be about ₹3.55 lakh crore.
How we built the numbers
Every figure comes from Table 1 of the MoSPI report, which lists original cost, latest revised cost and cumulative expenditure for each of 17 ministries and departments. We subtracted original from revised cost for each row and divided by original cost. Our sum of the 17 rows matches MoSPI's published totals for project count, original cost, revised cost and spending, to within one crore of rupees. The ministry split and every share in this piece are our calculations; nobody else has checked them.
We ran the same sums on the September report. The overrun was ₹3.22 lakh crore then, or 9.38% of original cost, against 9.43% now. That month-on-month move is small, and it is not a like-for-like comparison: MoSPI added 38 projects and recorded 24 commissioned in October, so the basket itself changed.
What the data cannot show
A revised cost is not the same as waste. Projects get re-costed when scope is added, land prices rise, designs change or a long-delayed job is priced at today's rates. The report gives no reason for each revision, so we cannot split the ₹3.28 lakh crore into delay, inflation and scope. The list also covers only central projects of ₹150 crore and above, the figures are reported by the ministries themselves, and finished projects drop out of the count, so the overrun on completed work is not in this total.
The counter-case to the headline is roads. The largest single book of central infrastructure has stayed within 1.5% of its approved cost, so the overrun is concentrated rather than spread across the pipeline. In the October data, two ministries with fewer than one in five projects account for seven of every ten rupees added since approval.